View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Question about consolidated working time - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Question about consolidated working time

More
27 Juil 2017 16:21 #1 by noisette
Dear all,
I have created, as suggested, a Administrative project to manage holidays & day off of the team.
Now, i would lile to know where and how I could know if the real working time of one of the resources is over the official working time.
I explain me : for example, A. has thee days off (holidays) and A. spent 100 hours working. So, in real time, I could fin that A. has "114 hours" for july.
But, A. has to work 154 hours.
Where and how I could see that for A., the real working time is 40 hours less than the official working time?

If A. work a lot in August, because he could end some project, and works 200 hours (it's just an example)... Where and how i could see that at the end of August, A. has 154 x 2 - (114 + 200) = 6 hours in overtime.
Etc.

All the best,
Christophe

Please Connexion or Create an account to join the conversation.

More
29 Juil 2017 00:40 #2 by babynus
You can have a look at repords (in Work and Planning section), but I'm not sure any will fit your need.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
08 Jan 2018 15:26 #3 by CNoisette
I tried several times to find in the different reports how to knw how many time one ressource has yet to do or if this ressource has over-worked... but I failed.
I think such a report could be very useful.
All the best
Christophe Noisette

Please Connexion or Create an account to join the conversation.

More
08 Jan 2018 22:32 #4 by babynus
Many planning reports will give that information.
Over work is not planned in ProjeQtOr.

Maybe you could describe what you expect exactly.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.