View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Why do all activities appear with a duration of 1 day in the planning view ? - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

5 juin 2025 (16h-17h30)

19 juin 2025 (16h-17h30)

9 septembre 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

18 et 19 juin 2025 (9h-12h30)

17 et 18 septembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai 2025 (9h-12h30)

25 et 26 juin 2025 (9h-12h30)

24 et 25 septembre 2025 (9h-12h30)

 

 

 

Why do all activities appear with a duration of 1 day in the planning view ?

More
31 Juil 2017 16:22 #1 by sger
Hi everyone,

I'm a new user and I'm facing diffultives in activities setup.

I've just created an activity with an estimated workload of 6 days.
This activity has been assigned to one member (100% capacity on the project).
I expected to see on the planning view a 6 days bar.

But the activity appears with a duration of one day.
Furthermore, in the activity view, in the 'planned days' column, only one day is indicated.

I don't understand why.
Could you explain me ?
Thanks,

Sandrine.

Please Connexion or Create an account to join the conversation.

More
31 Juil 2017 17:06 #2 by krowry
Hello ,

When you are on the screen "Planning" , click on the icon for calculate the planning ( see attachment ) .
Attachments:

Please Connexion or Create an account to join the conversation.

More
31 Juil 2017 17:09 #3 by sger
Thanks for your answer.

I tried it already but the planning didn't change.

Do you have another idea ?

Please Connexion or Create an account to join the conversation.

More
31 Juil 2017 17:10 - 31 Juil 2017 17:10 #4 by krowry
Can you give me a screenShot of your activity ?

Be sure you have selected " day " in Planning view ( see atachment )
Attachments:
Last edit: 31 Juil 2017 17:10 by krowry.

Please Connexion or Create an account to join the conversation.

More
31 Juil 2017 17:16 #5 by sger
The planning scale is correctly set.
You will find a screen copy attached.

Thanks for your help.

Sandrine.
Attachments:

Please Connexion or Create an account to join the conversation.

More
31 Juil 2017 17:26 - 31 Juil 2017 17:30 #6 by krowry
Can you verify the "capacity" of the resource " Thirion Lannister " ? ( he died on the episode 3 *joke*)

He can do few days ( depend of capacity ) in one day . You can have more detail of this in Report->Planning->Monthly Planning resource/project/activity .
Last edit: 31 Juil 2017 17:30 by krowry.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.044 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.