Hello,
yes but i launch each time, the scheduling calculation.
2.1 task
i didn't fill the field "rate (%)" for the resource "Guillaume".
I set an value.
Now, this task integrate the planning.
Q : right click on each bar permits to validate than the scheduling calculation ran correctly, isn't it ?
*** differences between "planning" and "planning per resource" ***
Below, the planning and the planning with a right click on 1.5 task.
The planning planned for Maxime, to work on 1.5 task the 23,24,25 August, while he is on days off .
Planning resource takes on board days off of Maxime.
I wonder if the click of the "validate planning" button explains that. If this the problem, i don't know if i can init again.
Planning :
Planning and right click on 1.5 task :
planning per resource :
project "rtt&congés" :
*** 2 resources on the same time of an task ***
1) constraint to skip than 2 resources on the same time work on an task ?
2) Can i set empty to "assigned" for 1.6 task, for Maxime and Guillaume ? I wonder if i can assign 2 resources on a task, and according to availability of resources, scheduling calculation assign number of days to each resource.
For example, task "C042", 3 days defined to terminate this task, scheduling calculation according to availability of resources, assign 2.5 days for Maxime and 0.5 day for Guillaume.
It is possible ? Assign task at a team (composed by Guillaume and Maxime) ?
Below, A05 task, 19 september, Maxime and Guillaume planned to work.
Thanks a lot, good afternoon.