ProjeQtOr free project management software - How does the Cost fields work in an Activity - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

5 juin 2025 (16h-17h30)

19 juin 2025 (16h-17h30)

9 septembre 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

18 et 19 juin 2025 (9h-12h30)

17 et 18 septembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai 2025 (9h-12h30)

25 et 26 juin 2025 (9h-12h30)

24 et 25 septembre 2025 (9h-12h30)

 

 

 

How does the Cost fields work in an Activity

More
29 Sep 2017 06:42 #1 by iconic
I created individual expenses for an activity, but the Cost fields in the Activity Progress Section doesn't seem to calculate or add the costs to the activity.

How does this work or what am I doing wrong.

Please Connexion or Create an account to join the conversation.

More
29 Sep 2017 09:31 #2 by babynus
Expenses are not "linked" to an activity, and creating a link between items does not provide specific calculation.
There is not functionnal meaning to the "link".

Expenses are summed as... expenses, on the project.
Cost only sums up cost of resource (from resource cost, defined on resource)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Sep 2017 12:39 #3 by iconic
When you say from Resource, I look at the Table of Resources I have and I can't seem to work out how to put the price or costing. Is there somewhere else I need to be looking at.

Please Connexion or Create an account to join the conversation.

More
29 Sep 2017 12:40 #4 by iconic
I guess based on my last question too. If I put a Bill to an Activity, that would not add the Bill price to the actual Cost in the Activity Window would it?

Please Connexion or Create an account to join the conversation.

More
29 Sep 2017 12:41 #5 by babynus

iconic wrote: When you say from Resource, I look at the Table of Resources I have and I can't seem to work out how to put the price or costing. Is there somewhere else I need to be looking at.

Look at the interface, not at the database.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Sep 2017 12:42 #6 by babynus

iconic wrote: I guess based on my last question too. If I put a Bill to an Activity, that would not add the Bill price to the actual Cost in the Activity Window would it?

No

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.