View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Bug with ticket Imputation? - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Bug with ticket Imputation?

More
11 Jan 2018 17:14 #1 by GIROUXC
Hi,

Look my attachments.

You will see a split tickets time ; 2 hour on "Planifier et assister les tests Mardi 16 janvier" on 08/01/2018.

But in the time sheet, you see 2 hours on Unassignment time. Why? Is it normal? I can not know where the 2 hours comes from.

In a other way, for the same type of split ticket time, we can see the time under his projet. That I feel normal.

Thank you
Attachments:

Please Connexion or Create an account to join the conversation.

More
11 Jan 2018 17:23 #2 by babynus
Replied by babynus on topic Bug with ticket Imputation?
The hours are referenced on the ticket.
They are correctly summed up on corresponding project, but on real work allocation, it is considered as "not planned work"

You can change this selecting "Planning activity" for the ticket.
This will link the ticket to the activity.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Jan 2018 19:37 - 12 Jan 2018 00:34 #3 by GIROUXC
Replied by GIROUXC on topic Bug with ticket Imputation?
Hi,
What you mean exactly?

Both tickets are not planned type (So, all my tickets in my projects are not planned type) and I saw only one with this behavior. They are not planned type in my default list. I do not think it's useful to add "Planned Ticket" in the list of types. Projeqtor does not recognize that, like any others type value of ticket that I can create, it is simple a text.

The help documentation say : Tickets : A ticket is a kind of task that can not be unitarily planned. Is not that exactly why the ticket is interresting, right? Following small unplanned tasks on a project or activity .I don't see the logic or any benefit of having an unplanned ticket disassociated from the parent project or parent activity when it's moment to put time. I see only disadvantages.


Can'you explain me?

Thank you.
Last edit: 12 Jan 2018 00:34 by GIROUXC. Reason: More details

Please Connexion or Create an account to join the conversation.

More
12 Jan 2018 08:40 #4 by babynus
Replied by babynus on topic Bug with ticket Imputation?
You're right : ticvkets cannot be planned. Just because you don't know them at project start.

But in some cases, you can plan some activity that will be to manage tickets.
This works fine for Support activities, Maintenance Activities, Waranty activities, ...
You can estimate at project start the time you'll spend on these tasks, and so book some time for resources.
And on thoose activity, you receive requests as tickets.
In ProjeQtOr, you can link Tickets to these planned activities so that :
- ticket is linked to the activity
- time spent on tikcet is subtracted from left work on activity
- all tickets are summed up on the activity

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
15 Jan 2018 15:56 #5 by GIROUXC
Replied by GIROUXC on topic Bug with ticket Imputation?
Hi,

I still do not understand why a ticket, comes in a non-assigned total under imputation. Would not it be more intuitive to add a "unassigned" line under the project rather to add a line without information at the top of the imputation. Because it may require us to create an activity only to instruct a ticket if no activity matches,. I think making the ticket less powerful.

But, I understand what you explain.
I will always put Activity in my ticket.

Thank you for you time

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.047 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.