View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Planning calculation - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Planning calculation

More
16 Mai 2018 09:13 #1 by bioN
Planning calculation was created by bioN
hello,
I think i don't understand very well how planning calculation is working on projeqtor.
For instance, i've got a project divided in some activities. The first activity was suppose to last for 3 days but when i allocate 3 days of work on that task i only get 68% of progress.
Plus it didn't reach 100% until i change the status of the activity from "in progress" to "done" and now the plannified date just change to the date i made the status change and now my project is planned to end later than i excpected.
I think i don't understand the calculation formula or i misunderstandthe tool.

thanks for helping.

Please Connexion or Create an account to join the conversation.

More
16 Mai 2018 09:34 #2 by babynus
Replied by babynus on topic Planning calculation
Progress = Real / (Real + Left)

So progress at 68% means you have some left work (I guess left is 1,4)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
25 Mai 2018 15:40 - 25 Mai 2018 15:40 #3 by bioN
Replied by bioN on topic Planning calculation
I figured out another issue with planning calculation.
When i want to plan a project in the future for instance asked Start date : 01/01/2019 and asked end date : 31/12/2019 and an activities asked Start date : 01/01/2019,asked end Date : 31/07/2019.
Then when i look on the planning i can see progress bar between the right dates but when i add on my project validate Start and end date (let's say i validate 10 days later than the asked dates) planning calculation run and progress bar are put at the date of the day.

Am i doing something wrong?

thanks for helping
Last edit: 25 Mai 2018 15:40 by bioN.

Please Connexion or Create an account to join the conversation.

More
25 Mai 2018 16:16 #4 by babynus
Replied by babynus on topic Planning calculation

asked Start date : 01/01/2019 and asked end date : 31/12/2019

How do you "ask" for dates ? Are they "requested" dates ?

If you just enter date, you dont' get a planning, but the drawing of a planning.
ProjeQtOr builds a capacity planning, and so needs to know work for each task, and who will work on the task.
Then date are calculated taking into account all contraints.

If you don't have work, you don't have planning (unless you set activities as "fix duration" planning mode.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.