View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - The management in ProjeQtOr - Page 4 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

The management in ProjeQtOr

More
08 Oct 2018 19:06 #19 by babynus
Replied by babynus on topic The management in ProjeQtOr

Do you have another document about pool of resources. We have already readen the user guide (using f1) but have difficulties knowing how it works.

Unfortunately not.

Each team is made up of different people. When the team leader wants to assign someone of his team to an activity, he changes the field « responsable », putting the name of the person concerned and taking of the team and do the same thing for the part « assignation ».
Then, he doesn’t calculate the planning again."

You can just add assigned work for the resource, it will be substracted from the pool ,automatically.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
09 Oct 2018 17:28 #20 by sogeti
Replied by sogeti on topic The management in ProjeQtOr
Hello,

I have another question about pool of resources.
I have created a pool made of 2 resources (for a test).
To realize my test, I have created a project with 2 activities Inside.
The 1st resource of the pool have made his allocations in the activity assigned to the pool (he is reponsible of the activity).
The other one has done the same thing for the other activity (he is also the responsible of the activity).

When I check the reports (planning => monthly planning resource/project/activity), I find 2 different results for each resources. They have exactly the same profile.

Here is the report for the 1st one :



Here is the report for the 2nd one :



Do you have any idea of where it can come from ?

Thank you in advance.
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Oct 2018 12:45 #21 by babynus
Replied by babynus on topic The management in ProjeQtOr
I guess PACKAPPLI is the pool, Toto 1 the first resource and Toto 2 is the second resource...

First report shows data for Toto 1, including work planned for the pool he belongs to.
As ha has nothing planned out of the pool, there is nothing else but pool data.

First report shows data for Toto 2, including work planned for the pool he belongs to.
Toto2 just sees his own real work additionnaly to pool data.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.060 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.