ProjeQtOr free project management software - Gantt Chart behaviour - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Gantt Chart behaviour

More
24 Oct 2018 23:56 #1 by Tom500
Gantt Chart behaviour was created by Tom500
Hi,

When you create an activity and save over a validated set of date ranges for example a week, and then change the status to assigned for example this then changes the Gantt to be the date you changed it to.

This doesn't help too well with planning, i tried changing the planning dropdown box to fixed duration and some others but this doesn't do anything and it still changed the gantt chart and assigns the validated dates into planned which in this example would become todays date.

Is there no way for the Gantt to just show validated dates?

Thank you

Please Connexion or Create an account to join the conversation.

More
25 Oct 2018 16:24 - 25 Oct 2018 16:24 #2 by alainforma
Replied by alainforma on topic Gantt Chart behaviour
Hello,
On the Gantt chart, ONLY calculated dates are displayed.
These calculated dates can sometimes be identical, and whatever the chosen planning method, to validated dates. Keep in mind ;-) that they have been approved by calculation before being displayed (or not) on Gantt.
For more information press F1 on gantt chart screen
Best regards
Last edit: 25 Oct 2018 16:24 by alainforma.

Please Connexion or Create an account to join the conversation.

More
26 Oct 2018 19:32 #3 by babynus
Replied by babynus on topic Gantt Chart behaviour
ProjeQtOr mainly uses "effort driven" calcuation.
So activities with no work assigned are not really calculated, except for "fix duration" planning mode.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.