Hi
Try and change planning calculation start date in the pop-up that triggers planning calculation.
Tried but nothing changed
Real work is not "calculated". It is entered by resources on Timesheet screen.
OK real work is entered on Timesheet screen but agregated (calculated) in activity screen.
Calculation takes into account "contraints" (assigned work, availability of resources, planning mode, dependencies).
In my example, task "Analyse du besoin" is "planned" between 01/08/2018 and 15/11/2018.
Mathieu started the 07/08/2018 and continued until 26/10/18. 3,81 days is done until now but he has to work 5 days more (left work) to finish the task.
Mathieu is available 20% for the project (1 day by week) and 100% by day for this task.
If I launch calculation since 01/11/2018, I imagined that projeqtor divide 5 days left in 5 weeks, so I expected a end of task planned at 29/11/2018.
As you can see on picture, planned end is equal with planned start (07/08/2018) : Why ?.
I tried to reproduce this issue on your demo database :
I created a project name "Projet TARZAN", I affected Analyst A, available 20% on the project.
I created a task "Analyse". I assigned Analyst A available 100%
On TimeSheet screen, Analyst A work 6, 7 and 8 august and then the 15 october.
5 days left work then I lauch calculation :
As you can see, end planned date is correct and Analyst A is planned 1 day by week as I expected
Regards