View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Precise calcul of projets - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Precise calcul of projets

More
27 Nov 2018 14:35 #1 by sogeti
Hello,

Can we calculate all assigned projets to a team, for one week, in one time ?

Please Connexion or Create an account to join the conversation.

More
28 Nov 2018 13:51 #2 by babynus
Replied by babynus on topic Precise calcul of projets

Can we calculate all assigned projets to a team,

No, this has no meaning, resources taking part to a project can come from different teams.
Buit you can calculate for the project you select.

for one week

Are you sure about the question ?
Planning for one week has no real meaning...
You must plan all left work, planning for one single week may have unexpected impact on planning for weeks after.

in one time

Yes, you can plan one or several or all projects at once.
For instance project leader can replan all his projects in one click.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Nov 2018 15:10 #3 by sogeti
Replied by sogeti on topic Precise calcul of projets
Ok,

Yes im sure for the "one week" ;). Sometimes we need to calculate Projets for one week.

In the view "planning", can we calculate projets only for one week ?
When i choose two dates in the view planning, it doens't work. I have all the projets.



Have you planned this change ?
Calculate only projets for one or two weeks ?
Attachments:

Please Connexion or Create an account to join the conversation.

More
28 Nov 2018 22:41 #4 by babynus
Replied by babynus on topic Precise calcul of projets

Yes im sure for the "one week" ;). Sometimes we need to calculate Projets for one week.

I still don't understand what is means.
Recalculating for a single week will have impact on following weeks that you won't see....

In the view "planning", can we calculate projets only for one week ?

No

When i choose two dates in the view planning, it doens't work. I have all the projets.

These dates only change visibility limit. it's only for display.
And I don't understand relationship with a week and a project.
Limit to a week won't limit to a project...

Have you planned this change ?
Calculate only projets for one or two weeks ?

Absolutely not.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Nov 2018 14:52 #5 by sogeti
Replied by sogeti on topic Precise calcul of projets
We use the pool, and on Friday, we change in the assignment field the pool by a human resource contained in the pool. So the calculate of the project will not impact the future. This Because we need for the next week (in the report view) a visibility on what human resources have to do, and over the following weeks, the pool charge.
And do to this, we need to change the assignment fiel, and calculate projet one by one. Its a lot of work.
But ok, its not possible to choose only projets on one week precisely

Translation in french :
On utilise le pool, et le vendredi, on change dans le champ assignation le pool par une ressource humaine contenue dans le pool. Donc le calcule du projet n'impactera pas le futur. Car il nous faut sur la semaine suivante (dans la vue rapport) une visibilité sur ce que les ressources humaines ont a faire, et sur les semaines suivantes, ce que le pool a comme charge.


"And I don't understand relationship with a week and a project."
Because we have a lof of projet realiz on one day, or 3 days max

Please Connexion or Create an account to join the conversation.

More
29 Nov 2018 19:08 #6 by babynus
Replied by babynus on topic Precise calcul of projets

So the calculate of the project will not impact the future

Yes it may !!!
Planning with a pool will insure one of the resources of the pool is available to work on the activity, but it may be not the one you selected as "human" resource.
So new planning may be different, and it's not sure that, even if pool could do the work on the activity the next week, the selected real resource will do so.

But no matter, replaning for next week "and following weeks" sould also be good. No ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.053 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.