View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Continuous activity - do not interrupt activity with another activity - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Continuous activity - do not interrupt activity with another activity

More
04 Jan 2019 00:04 #1 by Zoe
I've been spending time getting to know this application in order to use it for teaching Project Management at a university. So far so good!

My question is, is it possible to set an activity to be continuous?
Obviously, there will be weekends (and sick days ideally), but can I at least make sure that a resource won't be diverted to another activity halfway through the current activity? I know this is rarely relevant as most tasks can be dropped and picked back up, but I can't stop cooking roast dinner halfway through without it taking longer overall!

For example, I have two tasks that use the same resource (called "Atelier"). One of these tasks is part of the critical path but starts after the earliest start date of the other one. The result is as below. What I would like is for one of the tasks to be delayed such that neither is interrupted by the other.

Thanks!
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Jan 2019 09:20 #2 by alainforma
HI,

You can use either - the planning mode " must not start before the validated start date"
or - create a dependency beetween activities with a mode end-start.

Regards

Please Connexion or Create an account to join the conversation.

More
04 Jan 2019 19:51 #3 by babynus
There is no planing mode "not interrupted".
Only solution is one proposed by alainforma : add dependency so that second cannond start before first is ended.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Jan 2019 23:33 #4 by Zoe
Okay, so this is ultimately up to the project manager to notice and handle correctly by adding dependencies. Thank you :)

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.