View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Resource availability - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Resource availability

More
24 Nov 2011 12:27 #1 by ekolossov
Hi,
I have a question about setting up task: if i am setting task and assigning it to user without specifying the start date but with predecessor set and the duration specified and constraint as soon as possible I would expect this task will appear at the first available date for the assigned resiource but in Gantt chart I can see the link from predecessor to unknown time in past.
What I am doing wrong?
Another question: how to set up critical path?

Regards,
Evgueni

Please Connexion or Create an account to join the conversation.

More
24 Nov 2011 14:18 #2 by babynus
Replied by babynus on topic RE : Resource availability
You must replan the projet (calculation is not automatic).

Critical path is not managed in Project'Or RIA.
It is a identified evolution, not planned yet.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
24 Nov 2011 14:21 #3 by ekolossov
What you mean by replan the project?

Please Connexion or Create an account to join the conversation.

More
24 Nov 2011 14:25 #4 by babynus
Replied by babynus on topic RE : Resource availability
Recalculate : on Gantt planning view, click on button on left of the start date...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
24 Nov 2011 15:16 #5 by ekolossov
This have moved the predecessor start date to the beginning of the project not the date it have been scheduled

Please Connexion or Create an account to join the conversation.

More
25 Nov 2011 10:14 #6 by ekolossov
Ok, if I understand it right, I need to recalculate project FROM THE DATE OF PREDECESSOR start date. Am I right?

Regards,
Evgueni

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.062 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.