ProjeQtOr free project management software - [SOLVED] How to change number of hours per day - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] How to change number of hours per day

More
25 Mar 2019 12:36 #1 by clarezoe
I want to change the default number of hours per day however the field is greyed out. How can I change it? Thanks!
Attachments:

Please Connexion or Create an account to join the conversation.

More
25 Mar 2019 16:39 - 25 Mar 2019 16:41 #2 by alainforma
hi

You have just to change per hour by per day, Then you can modifiy the number and change once again per day by per hour. Be careful, in the interests of good reading, it is not recommended because of new numbers of hours, due to conversions, will be mentioned.
Last edit: 25 Mar 2019 16:41 by alainforma.

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 08:44 #3 by babynus
You cannot change when unit for work is hours and there exist some real work.
This is because all work data is stored by projeqtor in days.
So display of hours is a conversion.
As of today users have entered 8 hours for a full day.
If you change ratio, for instance to 7 hours per day, users returning to Timesheet will now see 7 hours where they entered 8 hours.
That's why it's lock.

Now, if you really want to change the ratio, there is a trick.
Chande work unit to days.
Save
Quit screen and come back.
Ratio is now updatable...
You can change it and get back to unit as hours...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 09:44 - 27 Mar 2019 10:07 #4 by clarezoe
Thanks! It's working now.

The reason I'm changing it is that we have some hours that we don't work on projects each week so the actual working hours are approx. 7 hours per day. When calculating planning it will calculate days by the number of hours per day right? So if I planned 56 hours for an activity for a resource who works 100%, it will be planned for 7 days however it is actually 8 days. Or is there any other ways to do it? I thought about the capacity for each person however it varies from time to time as well so I'd rather keep it as 1.
Last edit: 27 Mar 2019 10:07 by clarezoe.

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 13:00 #5 by babynus

When calculating planning it will calculate days by the number of hours per day right?

Well, in fact it will plan days, not hours...
So if you enter 56h, it will be done in 8 days for a 7 hours per day ratio, and in 7 days in a 8 hours per day ratio.

Or is there any other ways to do it?

You can play with capacity.
With 8h / day ratio, a resource will capacity 0,875 will be planned 7 hours per day so will execute a 56h tasks in 8 days.

I thought about the capacity for each person however it varies from time to time as well so I'd rather keep it as 1.

We will introduce variable capacity in a future verison ;)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 13:10 - 27 Mar 2019 13:15 #6 by clarezoe
That's exactly what I meant. So I can only set it to 7 hours per day to make the plan more reasonably, do you agree?

I see that the feature is planned in version 8.0, where will it be released? ;) I'm looking forward to it.
Last edit: 27 Mar 2019 13:15 by clarezoe.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.