View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Resource list blank when assigning to activities - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Resource list blank when assigning to activities

More
01 Avr 2019 13:54 #7 by clarezoe
Is that a 1st April joke? :')

We are not time travellers but we need to add projects that started earlier and continue the planning if you understand what I mean.

Please Connexion or Create an account to join the conversation.

More
01 Avr 2019 18:59 #8 by babynus

Is that a 1st April joke? :')

No, it is just a everyday type of joke.

We are not time travellers but we need to add projects that started earlier and continue the planning if you understand what I mean.

Then just don't set a end date to the allocation, you won't have any issue.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
02 Avr 2019 08:49 - 02 Avr 2019 09:06 #9 by clarezoe
If I don't set an end date then he will have 200% allocation if he has another ongoing project, won't the calculate go wrong in this case? I confirm that when I remove the end date, the names showed up in the list. But I don't understand why it doesn't show up when I have the end day while planning the resource within the allocated period.
Last edit: 02 Avr 2019 09:06 by clarezoe.

Please Connexion or Create an account to join the conversation.

More
02 Avr 2019 09:19 #10 by clarezoe
OK, I think I understand now. When I add a resource, it checks if the resource is available now, if I don't set the end date the person would be available for the project then I can change the date for the assignment.
Am I right?

Please Connexion or Create an account to join the conversation.

More
02 Avr 2019 09:32 #11 by babynus

If I don't set an end date then he will have 200% allocation if he has another ongoing project, won't the calculate go wrong in this case?

No, it will just tell that the resource has the hability to work at 100% on any of the project.
But the capacity of the resource will not be booked at 200%

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
02 Avr 2019 12:41 #12 by clarezoe
aha, now I know. Do you suggest that I set 100% on all projects and the assignment rate for different activities?

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.047 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.