View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Repport / Planning / synthesis of availability - Page 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Repport / Planning / synthesis of availability

More
26 Avr 2019 09:32 #7 by pipobru
Ok thanks for for this explain.
But when i define my pool with 3,9 ETP, 3 ETP on my task synthesis don't change. See sceen shot in attachement.


Attachments:

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 14:00 #8 by babynus
I thing you forgot to re-run planning calculation

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 14:16 - 26 Avr 2019 14:16 #9 by pipobru
Sorry but no i have re run planification calculation
Last edit: 26 Avr 2019 14:16 by pipobru.

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 14:58 #10 by babynus
I looked ar print screen more precisely.
On the activity, pool has 0,5 days left to do.
Whatever the ETP (1 or 3) it is done in less than 1 day, so ETP has no impact on planning

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pipobru

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 15:06 #11 by pipobru
Ok, but my problem is why the duration calculed is 4 days (no change when i add ressources in pool or modify ETP):

Attachments:

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 15:27 #12 by babynus
Possibly because resources of the pool are busy on other tasks.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 1.283 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.