View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Activities won't change their validated date automatically - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Activities won't change their validated date automatically

More
06 Déc 2011 08:05 #1 by blade
For example, I have two activities ( A and B) and the dated is list as follow. A is the predecessor of B.

Activities A:
requested Validated
starte date 2011/11/01 2011/11/01
End date 2011/11/07 2011/11/07

Activities B:
requested Validated
start date 2011/11/08 2011/11/08
End date 2011/11/10 2011/11/10

The question is when Activities A change its Validated start date to 2011/11/04 and End date to 2011/11/10. The Activities B won't change automatically. As I expect, the Validated start date of Activities B should be changed automatically to 2011/11/11 and End date shoule be 2011/11/14.

Please Connexion or Create an account to join the conversation.

More
06 Déc 2011 18:49 #2 by babynus
No,
Requested and validated values are not automatically updated.
There are here to keep a trace of initial values.

Requested : what the requestor wanted (requestor always request for yesterday :) )
Validated : the dates you committed on.

Then planned dates are updated depending on planning.

Planned evolution : propose to store planned date into validatred dates (kind of initial planning saving).


Regards.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
07 Déc 2011 02:34 #3 by blade
Thanks for your answer. May I ask one more question? planned date is read only. How this value be calculate? In my project, planed date seldom appear. In many times, planned date didn't show up.

Please Connexion or Create an account to join the conversation.

More
07 Déc 2011 10:05 #4 by babynus
You must replan your project to calculate planned dates.
Use small "gantt" button on planning view.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
08 Déc 2011 11:59 #5 by climb4fun
Babynus, it seems your customer/requstor seems to be identically with my one. :D
Have the same experience.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.