Planner calculation (last version)

More
02 Déc 2019 09:43 #1 by QUANTAMEDICAL
We encounter a logic problem in scheduling tasks. Here is the description of the problem:
Task to be prioritized
Project Priority: 270
• Predecessor element ending on: 06/02/2020 (# 2192)
• Collab Assignment to project: 30% (without specified start and end dates) - NB: even tested with 100% without change
• Planning mode: as soon as possible
• Collaborator alone on the task
• Task priority: 500 (# 2279)


Task however planned before:
Project Priority: 300 (# 16)
• Task priority: 500 (# 1957)
• Collab assignment to the project: 100% (all the time)
• Planning mode: as soon as possible

Many of the tasks in this second project are planned before, while the priority project task should be scheduled before.

Would you have a solution? a suggestion?

thanks in advance

Please Connexion or Create an account to join the conversation.

More
02 Déc 2019 10:08 - 02 Déc 2019 10:10 #2 by alainforma
Hello,

It could be plan after but never owe to be planed before or after. Planning calculation depend on dependencies and resources's disponibilities. Sometimes it could be explained also by the mode of planification you use on activities.
From now, it's missing some informations from your project to tell you why the calculation behaves this way.
Regards.
Last edit: 02 Déc 2019 10:10 by alainforma.

Please Connexion or Create an account to join the conversation.

More
02 Déc 2019 10:12 #3 by QUANTAMEDICAL
Thanks for your reply

No problem to give you more details on task or project concerned
Thank you for describing me the necessary additional information, I send it to you as soon as possible

Please Connexion or Create an account to join the conversation.

More
02 Déc 2019 10:20 #4 by alainforma

Please Connexion or Create an account to join the conversation.

More
03 Déc 2019 10:20 #5 by QUANTAMEDICAL
Hello,

I'm afraid we had a misunderstanding. Indeed, I need you to specify what you expect as additional information to identify the source of the problem. I would be happy to send you these items back.

Thanks

Please Connexion or Create an account to join the conversation.

More
04 Déc 2019 14:55 #6 by babynus
We need details (screenhshots) of 2 activities that you consider as not correcly planned : progress part, dependencies and assignments.
A screenshot of the planning showing the 2 activities.
Details of allocations of both projets.
Information of who is running planning calculation (profile, allocations,...).

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.