ProjeQtOr free project management software - [SOLVED] Incoming Issue - ProjeQtOr
 

[SOLVED] Incoming Issue

More
19 Fév 2020 14:40 #1 by karl.binet
Incoming Issue was created by karl.binet
Hi,

V8.3.3,

In the incoming windows, the value in "impact work" seem to be rounded in days

if i enter 40 hours, when we hit save the value is changing to 37,5 hours.

Expected behavior: keep efforts in hours as entered.

Regards

Please Connexion or Create an account to join the conversation.

More
20 Fév 2020 12:00 #2 by Flou
Replied by Flou on topic Incoming Issue
Hello,

Please specify on which screen you are.
In your global parameter, have you your unit for workload on hours ?

Please Connexion or Create an account to join the conversation.

More
20 Fév 2020 13:12 #3 by karl.binet
Replied by karl.binet on topic Incoming Issue
Hello,

My issue is in this screen

when i enter 40



i hit save it turns 37,5



And yes, in global parameter the workload is set to hours

Attachments:

Please Connexion or Create an account to join the conversation.

More
21 Fév 2020 12:23 #4 by Flou
Replied by Flou on topic Incoming Issue
Indeed there is an issue, we have created the tiket # 4507.
It will be patched on version 8.3.5.
In the meantime, just change the type to decimal(12,5) of impactWork on the DB for table Deliverable.
The following user(s) said Thank You: karl.binet