18 Mai 2020 11:33 #1 by fmt
Hi,

I have a remark on work assignement in meetings: il I modify meeting duration, attendees' assigned work does not align with ne meeting duration.

Regards,

fmt

Please Connexion or Create an account to join the conversation.

More
18 Mai 2020 15:36 - 18 Mai 2020 15:36 #2 by Flou
Hello,

it's not an issue, the creation of the assigned workload is only a help during the creation of the assignment and is not intended to be dynamically updated.
We cannot know if the load was modified after the creation of the assignment.
Last edit: 18 Mai 2020 15:36 by Flou.

Please Connexion or Create an account to join the conversation.