View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - resources costs per month report provide wrong results - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

resources costs per month report provide wrong results

More
22 Nov 2012 23:16 #1 by jphuart
Hello,

Maybe I've done some wrong costs assignements, but when I compare the following reports:
resources costs per month and cost synthesis per activity, the second is correct while the first is overestimated.

I don't know how to provide an example, but you can try at your level if it's the case.

Ciao
Jean Pierre

Please Connexion or Create an account to join the conversation.

More
24 Nov 2012 12:08 #2 by babynus
Ticket #911 recorded.

I'll try and reproduce.
If you can post a print screen or pdf export pointing out differences, it may help.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
02 Déc 2012 23:45 #3 by babynus
Hi,

I have the explanation of differences :
- "cost synthesis per activity" retreives costs from activities (real and left) : it is always up to date
- "resource cost per month" retreives data from planning : real costs, months by months, as entered by reosurces, and left work, months by months, as planned by Planning process.

If left work is updated on some tasks, these two reports will display differences, as long as planning is not run again.

Run planning calculation will resync "planned" and "real" values.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
03 Déc 2012 10:22 #4 by jphuart
It works. Well understood.
Thank you very much, now I understand better how the planning works and where do i have to perform corrections when plans changes.

I would like to create some custom reports, is there any documentation to allow me to avoid doing stupid errors on this?

Ciao
Jean Pierre

Please Connexion or Create an account to join the conversation.

More
03 Déc 2012 11:04 #5 by babynus

I would like to create some custom reports, is there any documentation to allow me to avoid doing stupid errors on this?

No, there is no documentation.
You will find some information in the forum, that will help you to start.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.