View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - The Planning FIXED DURATION has no affect. - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

The Planning FIXED DURATION has no affect.

More
28 Jan 2013 18:24 #1 by IC_PRQA
I required an Activity to have a fixed duration so entered Fixed Duration in the PLANNING field and the start and end dates in the REQUESTED and VALIDATED fields. When calculating the allocation of time it merely chose the next available time for that resource making it impossible to use this feature.

See also the Priority field blocking all ability to plan the resources time.

Please Connexion or Create an account to join the conversation.

More
28 Jan 2013 21:29 #2 by babynus
Fixed duration is designed to fix the ... duration.
So you don't need to set start and end dates, only validated duration.

This will fix duration of task, even if no work is assigned.
If work is assigned, il will behave like "as soon as possible", with just fixing duration. Duration can be more than validated only if resource availability is not enough to plan left work in the period.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
06 Fév 2013 11:18 #3 by IC_PRQA
thank you for the reply.
However I do not want something to act as Soon As Possible when I add times to the users. If I did then I would use As Soon As Possible.
What I want is that fixed duration is just that. Fixed I put the start and end times in and they are fixed.

Please Connexion or Create an account to join the conversation.

More
06 Fév 2013 15:17 #4 by ekolossov
You are asking not for fixed duration but for fixed timescale actually

Please Connexion or Create an account to join the conversation.

More
06 Jui 2014 11:42 #5 by IC_PRQA
I do not understand
Fixed duration is just the number of hours surely.

Fixed timescale is what I need to plan for.
I have to do some work between two dates. No choice regardless of other work to be completed.
This is impossible to enter into ProjeQtOr

Please Connexion or Create an account to join the conversation.

More
06 Jui 2014 21:02 #6 by babynus
Yes it is :woohoo:
It is regular between dates !

You enter validated start and end dates and assign work.
Work will be evenly dispatched beetwen dates.
You can also use "regular in 1/2 days" or "regular in full days".

RTFM :evil:

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.