ProjeQtOr free project management software - [CLOSED] PlanningElement_validation : Can not add float value - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[CLOSED] PlanningElement_validation : Can not add float value

More
29 Avr 2013 15:26 - 29 Avr 2013 16:59 #1 by vdeverre
When I put a float value (like 0,5) the post request send the good value but when I reload activity the field value do not show my float value. It's a rounded value.
Last edit: 29 Avr 2013 16:59 by vdeverre.

Please Connexion or Create an account to join the conversation.

More
29 Avr 2013 15:33 #2 by babynus
Which screen ?
Which field ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Avr 2013 15:51 #3 by vdeverre
Sorry.

It is in Activity, in the section Activity Progress.

You can check all input delay/charge.

Thanks.
Attachments:

Please Connexion or Create an account to join the conversation.

More
29 Avr 2013 16:24 #4 by babynus
Duration : only in full days, it is normal.
Project'Or RIA plans only in full days, so decimal duration has no meaning.

Work : decimal work works correctly.
Just be sure to use correct decimal point depending on your locale.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Avr 2013 16:48 #5 by vdeverre
We can not work half-day ?
Some activities not need a full day to be done.

When I put a "5.0" I have an error but not with "5,0" so input check the correct decimal point.

Please Connexion or Create an account to join the conversation.

More
29 Avr 2013 16:53 #6 by babynus
Yes, you can "Work" 0.5 day.
Work can be defined as decimal.
But this will be translated as a duration of 1 day.

Activity starting today and ending today lasts 1 day.
Project'Or RIA does not manage hours for start and end dates...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.054 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.