View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Refesh Gantt after calendar modification - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Refesh Gantt after calendar modification

More
11 Jui 2014 10:17 #1 by LU611
I've a problem when I change information in calendars.
Calculations are correct, but there is no change on the representation of working days or not.
It is necessary to disconnect and reconnect to see the changes.
Can you confirm this behavior? A correction is possible?
We are in the analysis phase before deployment and this is a problem for us.
Thanks.

Please Connexion or Create an account to join the conversation.

More
11 Jui 2014 12:07 #2 by babynus
Hi,

Do you mean that you change working/off days in a calendar and you don't see changes ?

Where do you expect to see these changes ?
=> in planning : only default calendar off days are displlayed
=> agenda : should be correct
=> real work allocation : should be correct

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Jui 2014 13:54 #3 by LU611
Hy,

absolutly !!!
I change just in default calendar .

So, in planner :

After change, in planning, the new off days isn't display in grey.
After disconnect/reconnect : it's OK.

In Agenda : it's correct immediatly

The real work allocation : it's correct immediatly.

Is it possible that the frame calendar isn't redraw and that just the gantt bar are recalculated ?

Please Connexion or Create an account to join the conversation.

More
11 Jui 2014 16:20 #4 by babynus

Is it possible that the frame calendar isn't redraw and that just the gantt bar are recalculated ?

No exactly.
It is because Gantt is drawn is Javascript, and using off days table stored in Javascrtipt.
And this list is loaded only on start page...

Ticket #1402 recorded to look for an improvement.
Does not seem to be blocking ;)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: LU611

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.