ProjeQtOr free project management software - Real work not counted for 'Cancelled' activities - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Real work not counted for 'Cancelled' activities

More
08 Juil 2014 18:09 #1 by caccia
Hi,

An activity can be cancelled even if real work has been entered. This is a real-life scenario, so no issue with that.
However, in the Planning view the parent project containing the cancelled activity does not take into account this real work, which seems strange to me.

For planned work, left work, etc. no problem, but I think real work should take into account all sub-projects & activities, regardless of whether they are closed or cancelled. After all, that real work has actually been spent ! :)

Attachments:

Please Connexion or Create an account to join the conversation.

More
08 Juil 2014 19:18 #2 by babynus
You are completely right : real work must be taken into account on real work sum for project, even if task is closed.

But I could not reproduce the issue you point out : anyhow I try it, project sum for real work is correct, even with a closed activity.
In the following exemple, Activity 1 is closed...


Could you remember how you came to your result ?
Any test case to reproduce ?

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Juil 2014 09:21 #3 by caccia
Hmm, note that this is only for cancelled activities, not closed I think.

I tried it on the demo site, see project #2 and activity #8.

Please Connexion or Create an account to join the conversation.

More
09 Juil 2014 15:30 #4 by babynus
Right !

It is due to evoluton to avoid to sum-up work for cancelled activities.
But, althought assigned work should not be consolidate, reald work should.
Ticket #1443 recorded

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.809 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.