ProjeQtOr free project management software - Spurious delay when planning with fixed milestones - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Spurious delay when planning with fixed milestones

More
29 Fév 2016 10:05 #1 by matthiaspnowak
We have a project, where several activities get a planned start much too late. This happened when we were trying to resolve a problem with a delayed delivery.

In short:
  1. a first fixed milestone
  2. a succeeding activity taking 20 days with planning as soon as possible
  3. a second fixed milestone, 10 days after the first one. This one has the previous activity as a predecessor - hence this milestone will be 10 days overdue
  4. a second activity, with the second milestone as a predecessor, planning as soon as possible

The Gantt-diagram shows the fixed milestone at its planned date, while planning cares about the planned data for deciding the planned start of the following activities. The attached picture shows what happens. I have been reading the code, but haven't yet found an appropriate solution. The fixed milestone should show a planned date much later (it doesn't), the diamond shown in red. The following activity should start the day after the fixed overdue milestone. Hence, it seems to be a bit more complicated to fix that bug.
Attachments:

Please Connexion or Create an account to join the conversation.

More
29 Fév 2016 11:27 #2 by matthiaspnowak
A simple fix is to change all milestones to floating milestone, but add a "validated due date". Then the planning will move the milestone to planned date in the Gantt, the diamond is colored red and the dependencies become obvious.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.