ProjeQtOr free project management software - [Milestone] - planned date - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[Milestone] - planned date

More
22 Fév 2017 18:03 #1 by VERGES
We have a critical issue about "planned date" milestone:

- When the milestone is "fixed" and validated or delivered:

The "planned date" shall be the same date than the "real date" when "done" is checked.
Now, the "planned date" corresponds to the "validated date" when the milestone is fixed.

- When the milestone is "floating" and validated or delivered :

The "planned date" shall be the same date than the "real date" when "done" is checked. During planification of the projet, even if the milestone is done, the planned date is updated and does not corespond to the real date. See an example attached.

To summarize, for all milestones, if "done" is checked ==>planned date" = "real date".

Please Connexion or Create an account to join the conversation.

More
27 Fév 2017 00:47 #2 by babynus
Replied by babynus on topic [Milestone] - planned date
Planned date (for milstones and for activities) is always result of latest planning calculation.
And when real is set, value is not planned any more.
This explains why planned date is always "last planned" date and is not equal to real.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Fév 2017 15:35 #3 by VERGES
Replied by VERGES on topic [Milestone] - planned date
Tnanks for your answer. I will check on the project where the issue has been tracked.

Please Connexion or Create an account to join the conversation.

More
01 Mar 2017 15:19 #4 by VERGES
Replied by VERGES on topic [Milestone] - planned date
Hello,
I've checked with the Project Manager and we always have this issue. You can find attached this problem.
In this example the real is set. (28/02/2017). The value is unfornutaly planned (01/03/2017).

It is a problem for the 45° curve too. Because, it is not the real date which is displayed but the false planned date. It is a big issue about reporting for ou client.

Also, concerning the 45° curve, when the real date is set before the planned date, the 45° cuve should be displayed the real date and not the planned date.

thanks you for your anwer,

Regards
Attachments:

Please Connexion or Create an account to join the conversation.

More
02 Mar 2017 11:30 - 02 Mar 2017 11:32 #5 by babynus
Replied by babynus on topic [Milestone] - planned date
28/02/2017 is the real 'done' date as you marked it done on this date

You should change the 'done' date to fix real end date ;)

Babynus
Administrator of ProjeQtOr web site
Attachments:
Last edit: 02 Mar 2017 11:32 by babynus.

Please Connexion or Create an account to join the conversation.

More
02 Mar 2017 11:43 #6 by VERGES
Replied by VERGES on topic [Milestone] - planned date
Ok to fix another real "done" date.

The issue is : "planned" date....

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.070 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.