No the human interaction is expected to happen as a routine.

That's not my point of concern.
Since the ticket is not competing with his project, the project tasks have remains unaffected.
But he is expected to work on the ticket.
So he will have to log much less real work on the project.
While he is working on the ticket(s), the remaining resources are also unaware of the delay building in the project.
Day by day, he will go on logging zero effort in the project.
There is no point in re-planning the project till he has finished the ticket.
And such tickets will be landing with multiple resources at different times.
This is not a good situation.
On the other hand, if the tickets were simply inserted in the Gantt chart, the new shape would be instantly known to everyone.
Another question is how exactly he will handle this on a daily basis, using ProjeQtor.
For example, he could stop using ProjeQtor till he finishes the ticket (say, a week).
Then he can update both the ticket and the project.
But this means the plan will get a new shape all of a sudden.