While using projeqtor on the timesheet view i get my real time on an activity "twice", on as "développeur" and the other one as "chef de projet"
2 ressources are working on that activty (id 165 and 191)
When i check on data base for these ressources i've got the same assignement ID for the same Activity and i don't know how it end up likes that.
Another thing is that when i go back into Activity screen and i update the assignement the ID are differents for the profil "Développeur" and "Chef de projet" so why are they equals in DataBase?
Developpeur A ssignement :
Chef de projet Assignement :
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.