View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Empty project automaticaly created after activity creation - Page 3 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Empty project automaticaly created after activity creation

More
22 Mar 2019 08:40 #13 by babynus

I already have made direct change on the database.

:evil:
This is always a bad idea.

But after each, It work fine.

:(
Side effects may appear later, possibly with new feature.
The framework expects some structure, that is not forced by DB model.
If you don't respect this, you may get unexpected behavior.

Try and apply consistency checks, on administration screen.
This may fix somet things.
But, as we don't know what you did on DB, possibly consistency fix will remove some data you consider valid.
So be sure to backup DB before consitency fix.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
22 Mar 2019 15:53 #14 by babynus
A fix has been found for "long duration" when ceating an activity.
It will be deployed on V7.4.4
Patch is attached.

Babynus
Administrator of ProjeQtOr web site
Attachments:
The following user(s) said Thank You: LaurentCap

Please Connexion or Create an account to join the conversation.

More
24 Mar 2019 12:28 #15 by LaurentCap
Hi,

I apply consistency check in administrator scrren and It make no changes. Activity creation takes 60 seconds.
But always update time on all the project changes instead of creating one.
Regarding the update date on project, I notice that the older is on the project at the most lower level.
Like the update apply on the project at the lower level and after the higher level and so on.

After applying fix It seems to takes more time (nearly 80 seconds).

Have you some other things that I can check ?

Thanks for your help.

A daily ProjeQt'Or user.

Please Connexion or Create an account to join the conversation.

More
24 Mar 2019 13:16 - 24 Mar 2019 13:17 #16 by babynus
Check last reply : patch proposed.

Babynus
Administrator of ProjeQtOr web site
Last edit: 24 Mar 2019 13:17 by babynus.

Please Connexion or Create an account to join the conversation.

More
25 Mar 2019 11:03 #17 by LaurentCap
Babynus,

I applied the patch and no changes was made. Always 60 seconds on Activity creation.

I continue to check idProject and refId + refType on all the tables.

Is it important to delete record of non-existing element in the tables history, kpihistory and kpivalue ?

Thanks for your help.

A daily ProjeQt'Or user.

Please Connexion or Create an account to join the conversation.

More
25 Mar 2019 16:28 #18 by babynus
Patch was not complete.
Good one is attached.

Babynus
Administrator of ProjeQtOr web site
Attachments:
The following user(s) said Thank You: Bena

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.053 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.