Assigning the workload to resources to perform an activity.
Some resources have external constraints, they can not begin until a fixed date.
Planning must take account of the start date of availability.
Thanks
Some resources have external constraints, they can not begin until a fixed date.
Planning must take account of the start date of availability.
I agree. And that's why affectation (to project) start date is a planned evolution.
But there should not be an assignment (to activity) start date for each assignment : it would be a mess to manage, a real slowing in planning calculation, and could lead to very strange planning calculation. Let's keep it simple.
Me:
To speed the entry of resource allocation, we can consider assigning a team?
1) Propose the team list with a checkbox (before the names)
2) Assign all resources selected in the activity.
You:
I registered the request as Ticket #786,
This ticket is very important.
It's very long to assign multiple activities many people.
There will not be a simple technique to select multiple people on one activity?
Thanks
Maybe in your case, but I never met such cases : in my opinion, no more than 2 or 3 resources should be assigned to the same activity. Otherwise, it's a mess to get planning that really means something.
It's very long to assign multiple activities many people.
There will not be a simple technique to select multiple people on one activity?
Not from the existing desing of application.
Moreover, when assigning a resource, you must select its function (may not be defined by defaut) and assigned work (may be different for each resource assigned).
Maybe you could describe your real need, because I don't get why you need to frequently assign many resources to many activities.
My problem :
I am working on "work units" (UO) with several activities and several milestones.
The team can go from 5p to 8p.
To manage projectorria I create one project (template) "work units."
Build the project is easy, but assign each activity 5 to 8p it's very long!!
I would like to simplify assigning.
My idea: Assign a resource (already) or a team. If it is a team, the tool assign to the activity list to resources (includes in the team). This does not affect the overall functioning but simplifies entry to assign.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.