03 Jui 2019 11:11 #1 by clarezoe
Hi,

I have an activity which has the planning mode "should not end before validated date", however the planning doesn't seem to work. What did I do wrong?
Attachments:

Please Connexion or Create an account to join the conversation.

More
03 Jui 2019 14:08 #2 by alainforma
Hello,
This software will attempt to respect the validated end date, but if a constraint exists elsewhere (generally the availability of resources that is insufficient) so it plans at the earliest but after the validated date because it indicates clearly the reality of things.
It means that is your job as Project Leader to find a solution to get what you want by modifying or cancelling constraints...

Please Connexion or Create an account to join the conversation.