View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Work weeks - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Work weeks

More
04 Jui 2019 12:13 #1 by tonyfj
Work weeks was created by tonyfj
Hi, I just using Projeqtor, I'm planning some projects.
One project must work 7 days a week so you have to count Saturday and Sunday. Does this have to be defined from a calendar, so that the calculation of workdays is accurate?
If so, is it possible to apply different workdays to several different projects? I mean, one calendet per project.

Thank you,

Antony

Please Connexion or Create an account to join the conversation.

More
04 Jui 2019 15:58 - 04 Jui 2019 16:37 #2 by alainforma
Replied by alainforma on topic Work weeks
Hi
We have adopted the following approach.
We plan the workforce of resources on opened days .
We apply a type of calendar for each resource. You can create as many calendars as you need. Then this single calendar type can list all the resources that can work for instance on Saturdays and Sundays ( let's think to close two another days during the week, general law in France) . So we do not take care of the project schedule as you expected. In fact, we consider resources working on a project (sunday - saturday) so the project is progressing automatically.
First go to global parameters then work time to unckeck saturday and sunday as days off; Then go to environmental parameter, then go to standard calendars, create one with saturday and sunday opened, then go to resource screen and fill it with the right calendar for each.
Regards
Last edit: 04 Jui 2019 16:37 by alainforma.
The following user(s) said Thank You: tonyfj

Please Connexion or Create an account to join the conversation.

More
05 Jui 2019 13:59 #3 by babynus
Replied by babynus on topic Work weeks
As a summary, you can define taht a resource works 7 days a week, but not a project.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: tonyfj

Please Connexion or Create an account to join the conversation.

More
09 Jui 2019 19:34 #4 by tonyfj
Replied by tonyfj on topic Work weeks
I got your point.
The problem is that both project run by the same PM. Even some project member are identical.

Antony

Please Connexion or Create an account to join the conversation.

More
11 Jui 2019 11:08 #5 by alainforma
Replied by alainforma on topic Work weeks
HI
you can prioritize projects using the index from 1 the most important, to 999 ( the less) and recalculate them.
The following user(s) said Thank You: tonyfj

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.