View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Making task progress on % of work completed - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Making task progress on % of work completed

More
07 Jui 2019 14:22 #1 by jyotidutta87
Hi,

I am new to this software. I have two questions. Please help.

(1) After creating the tasks list, to record the progress, I am filling the timesheet. Is it the correct way of recording progress of work?

(2) In the above method, actually I am recording the % of planned days utilized and on the Gantt Chart % progress comes accordingly. Is there a way to actually record progress of actual work? Example : If I have already worked for 50% of days, but actually work has progressed for 30% only, can I show on Gantt Chart progress as 30% thus reflecting true progress?

Thanks in advance.

Please Connexion or Create an account to join the conversation.

More
07 Jui 2019 16:10 #2 by babynus
(1) After creating the tasks list, to record the progress, I am filling the timesheet. Is it the correct way of recording progress of work?
Yes, absolutely
(2) In the above method, actually I am recording the % of planned days utilized and on the Gantt Chart % progress comes accordingly. Is there a way to actually record progress of actual work? Example : If I have already worked for 50% of days, but actually work has progressed for 30% only, can I show on Gantt Chart progress as 30% thus reflecting true progress?
Yes, you have to update left work (can be done on Timesheet or on Activity)
For instance, you are assigned 5 days to an activity.
You did 2.5 days (50% of assigned).
But 2.5 is not enough to finish.
So you change left work from 2.5 to (for instance to 6) so that you did 2.5 upon total of 8.5 (progress is about 30%)

NB : in most cases, entering left work is more accurate than trying to estimate current progress.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: jyotidutta87

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.