[SOLVED] Resources are not prioritized

More
26 Aoû 2019 12:15 #1 by clarezoe
Hi,

My resources are not prioritized for some tasks, for example, a recourse has 30 h work on Task A with priority 400, and another task B with priority 600 which is a very project and takes months to finish. When I do the planning he will start Task A for one day then do Task B, then after that finish Task A.

It's very frustrating, I don't know what I did wrong and where I can check to do the adjustments.

Thanks in advance!

Please Connexion or Create an account to join the conversation.

More
26 Aoû 2019 15:31 #2 by babynus
Be sure to replan both projects at the same time.
If you replan only one project, availability taken for the other won't be changed.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Aoû 2019 15:09 #3 by clarezoe
OK. That's why, thanks!