Remaining working time

More
12 Sep 2019 09:22 #1 by fmartin
Hello,

I was wondering if that is possible to adapt the calculation of the remaining working time to this:
validated work - real work = remaining work (with the percentage progress bar based on the result)

In our case, we create activities with a pool of days that we can't tell who to assign the work to. Basically, people work and record their working time in the activity.

Today, the remaining time is calculated between multiple values (validated work, real work, assigned, reassessed). This type of calculation makes it quite hard to follow the remaining work as all above values move when an employee record working time on the activity.

Best regards
FM

Please Connexion or Create an account to join the conversation.

More
12 Sep 2019 10:29 #2 by babynus
Replied by babynus on topic Remaining working time

I was wondering if that is possible to adapt the calculation of the remaining working time to this:
validated work - real work = remaining work (with the percentage progress bar based on the result)

If could be possible, if assigned work is not defined...
I recorded Ticket #4192, but not sure to implement this as it goes against general way of working in Projeqtor.

Today, the remaining time is calculated between multiple values (validated work, real work, assigned, reassessed).

No, Left is always Assigned - Real (if left is not redefined).

NB : You could do what you expect with a Pool
Allocate resources to a pool. Allocate the pool and the resources to the project. Assign the pool (and not the resources) to the activities (with assigned work)
Then resources can enter work on pool activities and left is correct.

Babynus
Administrator of ProjeQtOr web site