ProjeQtOr free project management software - Problem with imputations - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Problem with imputations

More
16 Sep 2019 10:38 #1 by lsigroup
Hi,

We are currently having an issue, here's the situation :
We have a collegue who badly entered his hours on an activity (he entered multiple days) this cause the entire planning (every next acitivtys) to be shifted because of this bad imputation.
This is very blocking for us

Regards

Please Connexion or Create an account to join the conversation.

More
16 Sep 2019 11:54 #2 by babynus
Replied by babynus on topic Problem with imputations
Sorry, I don't understand what is blocking.
If input is incorrect, just fix the input...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
16 Sep 2019 17:18 #3 by lsigroup
Replied by lsigroup on topic Problem with imputations
Because of the bad imputation my collegue entered,
The real time on this imputation is now 35,00 hours instead of 7
When whe are using the planning calculator the planified date changes because of that (in the example : 24/09/2019)

As you can see on the screenshot, we are unable to modify these values neither on the activity nor on the imputation.

Sorry if i'm not explaining very well, I'm doing my best but I'm not sure to understand everything either ...
Attachments:

Please Connexion or Create an account to join the conversation.

More
18 Sep 2019 18:00 #4 by babynus
Replied by babynus on topic Problem with imputations
Issue on planning is due to left 49h work.
You can set this to zero on activity screen.
No more work will need to be replaned so planned end date will be real end date, which is the laste date of input of work in Timesheet.

You must change real work on Timesheet screen.
If it is lock, it should be because Week is submitted or validated. Unvalidate / unsubmit the week to change data.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.