ProjeQtOr free project management software - How to highlight the Gantt bars when work haven't been start ? - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How to highlight the Gantt bars when work haven't been start ?

More
31 Jan 2020 10:29 - 31 Jan 2020 10:30 #7 by alainforma
It is weird. Try again changing a data or clean your browser cache
Last edit: 31 Jan 2020 10:30 by alainforma.

Please Connexion or Create an account to join the conversation.

More
31 Jan 2020 10:45 #8 by robertji
I have tried it again with changing a date and cleaning browser cache,
but it still not working.....

the planned date as same as validated date
Attachments:

Please Connexion or Create an account to join the conversation.

More
31 Jan 2020 10:52 - 31 Jan 2020 10:53 #9 by alainforma
You do not give any workload on this activity, you have just given a duration of 5 days; it is normal that the planning does not change. Please read the friendly manual to undestand how works Projeqtor and especially on various planification modes.
Last edit: 31 Jan 2020 10:53 by alainforma.

Please Connexion or Create an account to join the conversation.

More
31 Jan 2020 11:16 #10 by robertji
thanks,
so I still have to enter the real work in timesheet before ?

Attachments:

Please Connexion or Create an account to join the conversation.

More
31 Jan 2020 11:48 - 31 Jan 2020 11:51 #11 by alainforma
Have you assigned resources on activities with woarkload before ?
On time sheet :
Entering real work ( as planned) you are going to modify the % of progress.
Entering real work ( not as planned ) you are going to modify the % of progress and influence the next planification.
Entering a new left work you are going to modify the % progress and influence the next planification
Projeqtor always calculates plannings considering what has be done and what should be done at any present time to get the better view of the futur.
Last edit: 31 Jan 2020 11:51 by alainforma.

Please Connexion or Create an account to join the conversation.

More
31 Jan 2020 14:31 #12 by babynus
Or possibly you can define your activities with planning mode "fix duration", so that calculation knows whatr you want to do.
If you left default planning mode "as soon as possible", prpojeqtor expects some assiogned work to correctly plan the tasks.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.084 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.