[SOLVED] Type times (estimated times, spent time, workseet) by hour rather than day

More
12 Mar 2020 16:09 #1 by MagicBuzz
Hello,

When I create a task, or when I report times in the workseet, I must type days (0,5 = half a day).

We manage projects and maintenance, and we often need to type times hour by hour, or 15 minutes by 15 minutes.

As I France we have a base day length of 7 hours, it's very complicated to type 1 hour.
And it's simply impossible to type 15 minutes.

Is there a option to allow the user to type times using "hour" unit rather then "day" ?

Please Connexion or Create an account to join the conversation.

More
13 Mar 2020 14:25 #2 by alainforma
Hi,

Yes it is possible.
GO to global parameter / WORK / UNITS FOR WORK ;
Please note that 7h 8h or 9H etc is considered as 1 at the end of the day.
Please note that Projeqtor is a tool for managing whole project(s) and not to follow to the minute small time running tasks.
Regards
The following user(s) said Thank You: MagicBuzz

Please Connexion or Create an account to join the conversation.

More
20 Mar 2020 10:03 #3 by MagicBuzz
Thank you Alain,
I found the solution several minutes after my message, I didn't dig enougth in the configuration

Please Connexion or Create an account to join the conversation.