ProjeQtOr free project management software - How FTE variation works? - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How FTE variation works?

More
06 Avr 2020 04:21 #1 by rakoun
Bonjour,

I discover a very nice functionnality in Projeqtor, the ability to set FTE for a period.
So I set my ressource's default FTE to 1 and I set a COVID-19 FTE to 0.5 in "FTE variation" from 01/04/2020 to 31/05/2020.
But when I return to my gannt view and ask projeqtor to calculate my project, for a task with a charge of 8 hours it does not change its real spent time to 2 days but lets 1 day.

What is wrong in my configuration?

PS: 8 hours is my default number of working hour in a day

Regards,

Please Connexion or Create an account to join the conversation.

More
06 Avr 2020 10:38 #2 by babynus
Replied by babynus on topic How FTE variation works?
There's nothing wrong with your configuration, it's about undestanding what variation of capacity is.
It does not change duration of a day, so that a full work day is now half a day.
Moreover it won't impact real work entered.
It is just a way to plan the resource with a different capacity than usual one.
For exemple if you need the resource to work for extra time every day to cover some extra work during a period.
It can also be (for covid period) that the resource will be planned only half days during the period.
But it's only for planning, it won't have any effect on real work entered. It will just point out in timesheet that only 0,5 day is expected (sum for day is green when sum entered is 0,5), but resource is always able to enter more (or less) to reflect what he really worked.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
06 Avr 2020 11:42 #3 by rakoun
Replied by rakoun on topic How FTE variation works?

babynus wrote: There's nothing wrong with your configuration, it's about undestanding what variation of capacity is.
It does not change duration of a day, so that a full work day is now half a day.
Moreover it won't impact real work entered.
It is just a way to plan the resource with a different capacity than usual one.
For exemple if you need the resource to work for extra time every day to cover some extra work during a period.
It can also be (for covid period) that the resource will be planned only half days during the period.
But it's only for planning, it won't have any effect on real work entered. It will just point out in timesheet that only 0,5 day is expected (sum for day is green when sum entered is 0,5), but resource is always able to enter more (or less) to reflect what he really worked.


Thanks for the answer. So do I need to set my tasks charge to 50%?

Regards,

Please Connexion or Create an account to join the conversation.

More
06 Avr 2020 15:35 #4 by babynus
Replied by babynus on topic How FTE variation works?

Thanks for the answer. So do I need to set my tasks charge to 50%?

If you mean "assignment rate at 50%", NO.
Resource capacity to 0,5 will be enough to limit planning.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
13 Mai 2020 16:07 - 14 Mai 2020 15:09 #5 by rakoun
Replied by rakoun on topic How FTE variation works?
Hum...

Perhaps I did not understand.

Below my configuration with standard FTE of 1 and no variation:


And below a task in my planning with this configuration (task duration is 8h):


Now I change my FTE configuration inserting a period of variation with a FTE of 0.5 and keep a standard FTE of 1. (the example task is in the period and begin 15 june)


this is the result on my planning?


I expected that Projeqtor will put the task on two days and not only one day.

What is wrong?

Regards,
Attachments:
Last edit: 14 Mai 2020 15:09 by rakoun.

Please Connexion or Create an account to join the conversation.

More
14 Mai 2020 08:47 #6 by alainforma
Replied by alainforma on topic How FTE variation works?
Hello

Please , post on the forum directly to make it easier for our community

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.074 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.