ProjeQtOr free project management software - Error when calculating planning in view Planning (No data to display) - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Error when calculating planning in view Planning (No data to display)

More
24 Avr 2020 02:17 - 24 Avr 2020 02:18 #7 by msassi
Hello,
It seems that reason that you sent to me are not tthe cause of my problem.
I ckecked it one by one in my project but problem is not resolved.

I taked 14 screenshots from differents UI in my ProjeQtor that I thought they could contain the cause of my problem.
Please find in attached a .zip

We choose projeqtor between many are solution because we like too much how planning is calculated.
Hope that we could together find solution for this.

Thank you in advance
Attachments:
Last edit: 24 Avr 2020 02:18 by msassi.

Please Connexion or Create an account to join the conversation.

More
24 Avr 2020 09:04 #8 by babynus
Hi,

Your resource #3 has capacity (FTE) = 0
It means he can work 0 days per day.
This explains why the planning gives no result.
Chenge Capacity to 1 (standard value) to have planning work.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
30 Avr 2020 18:09 #9 by msassi
Hello,
After following your last mail, we have only one problem resolved. (in relation with timesheet)
Now, colors in timesheet are well displayed ('Green' for all working days with 8 hours and 'Red' for off days).

But, planning calculation still not working !

Any help please. Could you take a look again to all screenshot that I sent in others messages.

Thank you in advance.

Please Connexion or Create an account to join the conversation.

More
01 Mai 2020 14:43 #10 by babynus
When capacity is fixed, recalculate planning.
If planning is not calculated, check allocation rate to project : it must not be 0 on projct and on parent projects.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
01 Mai 2020 16:30 #11 by msassi
If we well understand "Rate", it's column "Rate" into project/Allocation to project.
Please take a look to screenshots we attached to this ticket and check with us if rate is well done.

Else , we always have doubt that probems are caused by fields into "Dates and durations" into every activity. There are always empty.
But when ressource fills into timesheet and "real time" of activity becomes > 0, planning is well calculated (Look please to screenshots called "Real_time_1.png" & "Real_time_2.png")
Attachments:

Please Connexion or Create an account to join the conversation.

More
02 Mai 2020 14:17 #12 by babynus
Hi,
On your screenshot I can see that left work is zero.
So there is nothing more to plan...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.