View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] activity

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] activity <1day

More
01 Sep 2021 13:25 #1 by Florian_APSIDE
Hello,My problem when I have activities <1 day, the management of projeqtor does not seem correct to me.

Indeed if I have 2 activities of 0.5 days I would expect these 2 activities to end at the end of one day, but under projeqtor ends during the second day.

Do you have a solution?

Thanks,
Florian

Please Connexion or Create an account to join the conversation.

More
01 Sep 2021 14:19 #2 by babynus
Replied by babynus on topic activity <1day
This happens if you add dependency between tasks.
Defautl dependency mode is "strict", meaning that if predecessor end day D, successor will start at D+1
You can change this behavior in global parameters.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.