View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - manual planning & planning calculation - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

manual planning & planning calculation

More
31 Jan 2022 16:18 #1 by vba
Hello team.

I'm trying to adjust end date of a manual planed task.
There is no assignement, the predecessor is closed, and i do not modify the start date, only the end date to adjust duration.
I ran planning calculation. Others task correctly adjusted but not this one.
AFAIK there are not other constraints on this task.

Is there any way to view some sort of calculation trace to see what could be the cause?
Thank you for your great support
Attachments:

Please Connexion or Create an account to join the conversation.

More
01 Fév 2022 09:12 #2 by Arkhanje
Hello,

Manual planning, as its name suggests, is planned exclusively by hand and takes priority over all other planning modes even without any constraint.

To modify the planned dates in this mode, edit the assignment on the activity or go to the "planned interventions view" screen to view and modify the assignments.

The schedule calculation will never modify your schedule in this mode.

Please Connexion or Create an account to join the conversation.

More
01 Fév 2022 09:49 #3 by vba
Thank you for your reply and help.
Does this mean an assignment is mandatory to a manually planned task?
I just would like to manually set start date and end date to this task which represent a given period of time, but with no assignment on it.

Please Connexion or Create an account to join the conversation.

More
01 Fév 2022 09:58 #4 by Arkhanje
yes, there is no point in working without assignment and assigned workload for the manual planning mode.

the "fixed duration" planning mode should work for you.

Please Connexion or Create an account to join the conversation.

More
07 Fév 2022 15:12 #5 by vba
Thank you for you reply.
Unfortunately the only way to modify duration -- and end date -- in my case was to drag the bar on the gantt chart. And this, whatever scheduling options i choosed. Then, the dates within the activity, and the gantt reflected correctly the given date/duration.

btw, thank you again for your support.

Please Connexion or Create an account to join the conversation.

More
08 Fév 2022 09:35 #6 by Arkhanje
I'm not sure why this would be the only solution, but you can drag the bar of an activity in "fixed duration" planning mode directly onto the Gantt.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.