View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - resource planning - column responsible shows assigned resources? - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

resource planning - column responsible shows assigned resources?

More
10 Aoû 2023 10:00 #1 by OliverOde
Hi 

An activity can have multiple assigned recourses, but only one responsible.

However, in the resource planning, the assigned resource is displayed in the responsible column, even if this resource is not responsible.    

Can this be changed?
If not, what is the idea for this behavior?

Thanks in advance
Greetings
Oliver

  

Please Connexion or Create an account to join the conversation.

More
10 Aoû 2023 10:23 - 10 Aoû 2023 10:26 #2 by Plucks
Hello,
You may check (connected as an administrator) in Global Parameters, Planning tab, Automation, "auto set responsible if needed", and below "auto assign responsible to activity"
 
Attachments:
Last edit: 10 Aoû 2023 10:26 by Plucks.

Please Connexion or Create an account to join the conversation.

More
10 Aoû 2023 10:50 #3 by OliverOde
Hi
Thanks for the quick response, but unfortunately the setting does not help.

In the example you can see that several resources were active on the same activity, but Stefen is responsible for all activities.

Basically the column is just a repetition of the grouping.
 


So the question remains if this can be changed.

Greetings
Oliver
Attachments:

Please Connexion or Create an account to join the conversation.

More
14 Aoû 2023 18:39 #4 by babynus
You're right.
In the resource planning, the data in the column "Responsible" is the name of the current resource (the resource under which the activity is displayed).
Ticket #7338 recorded

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
16 Aoû 2023 15:27 #5 by OliverOde
Thank you
everything is fine in V10.4.4

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.091 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.