View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How work pool ? - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How work pool ?

More
08 Fév 2024 16:26 #7 by loicr
Replied by loicr on topic How work pool ?
the pool seems to work as a complete // entity who is taken into account capacity of team when you assign it but it works only in one way ... on the other hand when my 2 contributor are full during 2 month, the pool who normaly should agregate colaborator say : disponibilties is 300h ... its wrong .. i don't planned the pool (agree) but pool is compose by 2 peoples 100% full so disponibility of pool should say me 0% of disponibilities ...
i really don't understand.

I remeneder this trouble and this is why we are not able to work with pool.
Also in planning by ressources we are not able to know the ressources taken into account by the pool for making a task.

LR

Please Connexion or Create an account to join the conversation.

More
08 Fév 2024 17:44 #8 by alainforma
Replied by alainforma on topic How work pool ?
Now i understand much better ! I will have a look about that and i will come back.

Please Connexion or Create an account to join the conversation.

More
09 Fév 2024 09:23 - 09 Fév 2024 09:24 #9 by alainforma
Replied by alainforma on topic How work pool ?
You are right. Pool does not take into consideration the planified work of its resources to set its own availability. To be honest, it will be quiet difficult to implement this calculation, nevertheless it could be considered with sponsoring.
Last edit: 09 Fév 2024 09:24 by alainforma.

Please Connexion or Create an account to join the conversation.

More
09 Fév 2024 09:31 #10 by loicr
Replied by loicr on topic How work pool ?
Thanks to confirm our trouble.
The only good adventage of pool is for us to assign group of people in a task.
But according this point and the fact we are not able in details planning to know the contributor taken into account by pool we are not able to use it.

Thanks for your support.
LR

Please Connexion or Create an account to join the conversation.

More
10 Fév 2024 11:15 #11 by babynus
Replied by babynus on topic How work pool ?
This is a point we must improve.
Availability reports show availability for pools taking into account work planned on the pool only, not the work planned on the members of the pool

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: loicr

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.