Hi,

In timesheet validation, there is a column with an expected number of hours for each resource.

 

These expected hours are not in sync with the employee contracts.
So, where can I set this expected number of hours for each resource / employee ?

Thanks
Franck
Attachments:

Please Connexion or Create an account to join the conversation.

More
12 Fév 2026 15:12 #2 by maxca
Hello,
Expected: corresponds to the number indicated on the “capacity (FTE)” resource multiplied by the number of days.
Have a nice day,

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.