View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Planning - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Planning

More
26 Sep 2012 16:06 #1 by JCDe
Planning was created by JCDe
Hi,

  • Constraint planning "as late as possible" needs an end date. Is it possible not to be completed if a milestone is the successor, and take the date of the milestone?

  • I have a particular constraint, I want to start an activity in same time as another, but :
    1) To start my activity, the other must be started.
    2) I can not finish this before the first activitée.

    So is it possible to manage these constraints
    1) Must start after starting an activity.
    2) Can not be completed before the end of the other activity.

  • thank you

    Please Connexion or Create an account to join the conversation.

    More
    26 Sep 2012 19:12 #2 by babynus
    Replied by babynus on topic Re: Planning

    Constraint planning "as late as possible" needs an end date. Is it possible not to be completed if a milestone is the successor, and take the date of the milestone?

    Really, I don't know how to do this. But it seems an interezsting idea. I recirded the request as Ticket #793.

    Babynus
    Administrator of ProjeQtOr web site

    Please Connexion or Create an account to join the conversation.

    More
    26 Sep 2012 19:18 #3 by babynus
    Replied by babynus on topic Re: Planning

    So is it possible to manage these constraints
    1) Must start after starting an activity.
    2) Can not be completed before the end of the other activity.

    1) No, relations are only end-start.
    3) Neither.

    Only thing you can do is play with priority : higher priority (smaller value) for first one, lower priority (higher value) for second one, and adding a milestone before both, they should start on same time, possibly hte second after the first (because of priority). But this will not be assured.

    Babynus
    Administrator of ProjeQtOr web site

    Please Connexion or Create an account to join the conversation.

    More
    26 Sep 2012 21:28 #4 by JCDe
    Replied by JCDe on topic Re: Planning
    That's what I thought :huh: ...
    In case I hoped a miracle solution :P ...
    thank you

    Please Connexion or Create an account to join the conversation.

    Moderators: babynusprotion
    Time to create page: 0.033 seconds

    Paramétrages de cookies

    ×

    Cookies fonctionnels

    Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

    Session

    Veuillez vous connecter pour voir vos activités!

    Autres cookies

    Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.