View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Shifting Planned Start and End Dates - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Shifting Planned Start and End Dates

More
05 Aoû 2015 17:54 - 05 Aoû 2015 17:54 #1 by oracleraj
Hi,

I have a very small project that lasts for a week with 3 resources. Due to resource crunch i've asked the two resources to stretch the working hours (more than 8 hours) and complete the task in one week itself.

But though i set "Fixed dates" mode and assigned resource with days (7.5/week), after "Calculate activities planning" the dates are shifting to adjust 8 hours / day and the Project's planning dates are moving to 1.5 weeks. I don't want to change working hours >8, because it impacts other projects too.

Is there any workaround for this?

Thanks
Raj
Last edit: 05 Aoû 2015 17:54 by oracleraj. Reason: symbol

Please Connexion or Create an account to join the conversation.

More
05 Aoû 2015 18:00 #2 by babynus
A workaround is to increase resource capacity.
(as it is exactly what you request)
But take care as this will be applied to all projects of the resources.

Another workaround (my prefered) can be to consider that left work is just 5 day (even is assigned work is more).

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.