ProjeQtOr free project management software - [SOLVED] Split the workload - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Split the workload

More
11 Jan 2016 11:55 #1 by Breuu
Split the workload was created by Breuu
Good morning,

First of all, I would like to wish you a great and happy new year! :)
Secondly, I would like to congratulate you for this excellent tool.

I am performing some tests for my internal needs and the results are very interesting.
I am encountering some trouble of synchronization between my WBS and my GANTT but it is possible it was a human error from my side.

By the way, I am trying to split the workload for a dedicated ressource.
To be more clear, I would like to limit the number of day per week for my project manager (2 days per week).
I tried to use the attribute "rate" but unfortunately nothing changed in my GANTT.
Do you know how to proceed?

Thanks a lot

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 13:50 - 11 Jan 2016 13:50 #2 by babynus
Replied by babynus on topic Split the workload

To be more clear, I would like to limit the number of day per week for my project manager (2 days per week).

It is exactly what will the affectation rate on the project : set to 40% will limit work at 2 days per week.

I tried to use the attribute "rate" but unfortunately nothing changed in my GANTT.

Once changes are done, you need to run planning calculation to take changes into account.

Babynus
Administrator of ProjeQtOr web site
Last edit: 11 Jan 2016 13:50 by babynus.

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 14:20 #3 by Breuu
Replied by Breuu on topic Split the workload
Thanks a lot for your reactivity.

I understand that "rate" is the attribute to split the workload.
Unfortunately, I don't understand the way of working.
Let me explain you (sorry if it is a basic question):

There are the attributes:
- assigned: It corresponds to the targeted number of days for an activity
- duration: It corresponds to the duration of task which can be different of the "assigned" attribute

Firstly the attribute rate is only dependant to the attribute "assigned", but it seems to be logic.
You can use Duration or Assigned independently but if you set both attributes, only assigned attribute will be taken into account in the GANTT

My problem is, if I set:
- Assigned: 1 day
- rate: 50 %
--> the GANTT is showing me 3 days of duration but normally it should be 2 days. (see the screenshot attached)

Is it a mistake from my side?

Thanks
Attachments:

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 15:13 #4 by babynus
Replied by babynus on topic Split the workload
Several possibilities to explain the behavior :
1) Capacity of resource if < 1. So full day for the ressource is < 1, 50% is < 0,5, extending duration...
2) maybe resource is busy on another task, on another project....
3) maybe resource uses a calendar with closed days during the period

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 23:18 #5 by Breuu
Replied by Breuu on topic Split the workload
Thanks a lot for your patience!
It was your first assumption :blush:

I will continue my tests!

See ya!

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.