ProjeQtOr free project management software - [SOLVED] Activity with planned date in progress is red - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Activity with planned date in progress is red

More
21 Jan 2016 11:07 #1 by igio80
Hi, I don't understand because in an activity planned date is red and not editable.
I set this activity with a start and end date validated. I assign activity to a resource setting only 100% rate (this resource has committed for now some real work days). In this activity duration is 19 days but in planned column duration is 30!!! Why? Where am I wrong?
Thamks

Please Connexion or Create an account to join the conversation.

More
21 Jan 2016 14:56 #2 by igio80
Found solution. I must manage correctly left work.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.