ProjeQtOr free project management software - How to put a planned date on an activity - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How to put a planned date on an activity

More
09 Fév 2016 13:23 #1 by dnaton
Hello,

When I create an activity, I can put "start date requested" and "start date validated", the same for end date.

but how can i put the planned date ?

I thought it was on the planning of the ressource affected to the activity but I didn't find anything.

Can someone help me ?

Thanks

Regards,
Damien
.
ProjeQtOr v11.0.1 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : Personalized Translation 1.5 - Customization of screen 6.6

Please Connexion or Create an account to join the conversation.

More
09 Fév 2016 14:28 #2 by richard.pare
Yes, planned dates are defined according to assigned work defined for resources to tasks.
For the first draft of project plan, you can use validated dates or requested dates to defined planned dates.

Please Connexion or Create an account to join the conversation.

More
09 Fév 2016 14:34 #3 by dnaton
Thanks for help, but I don't understand all you tell me :(

I've assigned work to a ressource for a specific taks but the field "Planned" is still empty (see image below)

Regards,
Damien
.
ProjeQtOr v11.0.1 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : Personalized Translation 1.5 - Customization of screen 6.6
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Fév 2016 14:42 #4 by richard.pare
Are you executing the process to calculate planning?
The process can be started in the Gantt chart.

Please Connexion or Create an account to join the conversation.

More
09 Fév 2016 15:04 #5 by dnaton
Fine : it works.

I didn't know this functionnality.

Thanks

Regards,
Damien
.
ProjeQtOr v11.0.1 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : Personalized Translation 1.5 - Customization of screen 6.6

Please Connexion or Create an account to join the conversation.

More
09 Fév 2016 15:14 #6 by richard.pare
It's my fault!
I rewrite the user guide.
Next version will contain this information.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.